Ask HN: Do you think Agile/Scrum is beneficial for software delivery?
449 pointswhat are the pros and cons of sprints and daily standups in your experience
Coming from old school 'non-agile' financial world focused on bottom line I was in a bit of a shock learning about this daily standup ritual.
Besides being a dream for micromanagers, it seems to be more about signalling progress vs. actually making progress.
Do these extra bureaucracy layers, meetings, checkmarks and vague "man-points" estimates actually bring any value.
Comments (695) 225 threads
Earlier commentsAgility is just what it says: a philosophy of flexibility and adaptiveness.
Heirarchies, heavy processes, etc are by definition inflexible. They are not agile. You do not do agile. You are agile. You are agile because your company has a culture that is agile and you cannot achieve that unless the company is structured to be flexible.
I think actual agility is really, really a great way to build software efficiently... but unfortunately most programmers will only experience the cargo cult forced upon them by certified scrum masters... and this is just as bad, perhaps worse, than old fashioned waterfall.
More than anything, working in an agile environment is a very pleasant thing to do from a human standpoint. But most companies are incapable of the kind of equality and empowerment necessary to achieve agility, so they will force the terrible cargo cult version upon us.
Scrum (as intended, not as actually done in most companies) is in essence a set of rules to prevent things from falling apart after you have ditched the managers:
* know what you want to achieve during this month -- planning for longer time is unrealistic, weekly planning is micromanagement;
* at the end of the month, make a demo of new features -- make sure that all pieces fit together, and get feedback whether this is actually what the customer wanted;
* reflect on what happened during this month and why -- this is the moment to speak freely, complain, and propose changes (for example, this is the occassion when the developers could collectively decide to stop using Jira);
* decide where to go during the next month -- together with the customer: the customer decides "what first", developers decide "how fast";
* make sure your colleagues know what you do and whether you need help -- this shouldn't take more than 3 minutes a day.
If your sprints are weekly, you are doing it wrong. If you don't make a demo, you are doing it wrong. First, with continuous integration, deploying the demo should be trivial. Second, if you don't show the demo to the customer, who is giving you feedback on your progress? (Nobody? Management?) If you skip the retrospective, or if you don't feel free to speak openly during the retrospective, you are doing it wrong. If you don't have an idea what to do next, and what is important for the customer, you are doing it wrong. If management gives you deadline, you are doing it wrong. If your daily standup takes more than three minutes, you are doing it wrong. (For anything that requires more time, you should arrange a separate meeting, for only the people involved, not the whole team. Note that the "separate meeting" could still be like five or ten minutes long.)
So much for the dream. Now here is what actually happens: in your company, the managers have the power, and they are not going to fire themselves. So instead, they will impose on you some kind of management-driven pseudo-Scrum, which looks like this:
The sprints are short, because that gives the managers greater feeling of control. You don't talk to the the actual customer, and the customer doesn't see your product before it is officially delivered; the managers acting as middlemen is how they justify their jobs. There is no retrospective, because this is the first and the last time in history when management decides that something is a waste of time. You have sprint planning, but you also have deadlines, so your choices are often limited to "do X this sprint and Y next sprint, or do Y this sprint and X next sprint". The daily, instead of team members synchronizing with each other, becomes team members reporting to the manager. You get Jira, which is set up according to the manager's wishes.
This is not a coincidence. The managers insist it needs to be done this way, because they want to protect their jobs. The same thing would happen with any other methodology.
That's the gold standard! You know you are doing fake agile when the team is not allowed to decide stop using Jira.
In all seriousness, thanks - very valued insights! I did not even know those were the original purposes of the Scrum ceremonies, having only ever worked witn almost exactly the kind of pseudo-Scrum you describe.
This is the moment you know you are doing fake Agile and your scrummaster is just the managers puppet in disguise to spy on the team.
Continue this thread — 1 reply
We still had retros and dailies. Planning was done by managers explaining a feature they'd like us to do, and the team then doing the planning, design and implementation. More processes and e.g. recurring meetings were erected and torn down based on the team's actual needs alone. If someone wanted an estimate, we'd give it, but we were not doing continuos estimation just for the sake of estimation itself, like in Scrum. Felt like the process served us, rather than us serving a process. If you'd taken a look at the Agile manifesto, we were ticking pretty much all the boxes: https://agilemanifesto.org/principles.html
Then 1.5 years ago, company decided to roll out whole IT department wide SAFe, which is basically Scrum but on a whole organization level, and hence even more bureaucratic and with one additional level of mega-iterations added on top of Scrum's sprints.
Suddenly, our team is assigned a Scrum master and we no longer even get to speak directly with the managers who previously negotiated new features with us. Instead, everything has to go through multiple levels of prioritization and broken telephones of new SAFe intermediaries. We started attending 2-3 new mandatory processes / recurring meetings, meaning time spent in inefficient boring meetings went up significantly. We had to also start a much more stringent ticketing system regime, including having to estimate ALL work. Despite multiple requests from Scrum master and managers, nobody was ever able to explain why estimating absolutely everything - even when nobody had even asked for an estimate - helped with anything. It was seemingly taken as a religious thesis that it was just the right thing to do.
Soon, the team was paralyzed. Even simple features became harder and harder to develop. Despite the massive effort spent on estimating even the most trivial of tasks, the big picture was forgotten about because larger feature-level ballpark estimates were no longer acceptable, and hence unimportant. On a company level, the business managers that previously talked directly to us just basically quit working with the IT department because the SAFe process was such a beast to contend. It was easiest for them to just stop asking for new digital product features, and focus on non-IT projects instead.
I know Scrum / SAFe proponents will say we were doing it wrong. It's ALWAYS that way - Scrum consultants love to gloat when some metric improves, but if things go south the org has only itself to blame for failing to correctly convert to their favorite flavor of True Agile System™.
My experience was however seeing an Agile team (as expressed by the Agile manifesto) turn into a Monty Python parody of agile software development just by being forced to submit to these "fake agile" heavy processes and hierarchies.
There are a set of ‘good things’ that I can see from SAFe, and if you read the book and do the course there is loads about how you /should/ adapt it to work for you.
Amongst the issues is that SAFe, by its very nature, has stakeholders outside the local team and that mandates some sort of process.
Interestingly the size that Scaled Agile talk about is pretty big - a small Agile Release Train was discussed as ~100 people across ~5 teams. The full Portfolio SAFe is for multiple release trains e.g. 500+ people.
If you’re trying to enforce SAFe on something much smaller then I think you’re probably doing it wrong.
Also, if the “IT Department is trying to implement SAFe” rather than the “Company is undergoing a SAFe transformation” it has already gone wrong. You need to have your stakeholders throughout the organisation on board, and it is something of a top down thing.
the comment you are answering was on point
>I know Scrum / SAFe proponents will say we were doing it wrong. It's ALWAYS that way
Continue this thread — 3 replies
Is this really happeninig in your org when adopting SAFe? At least for us - we went to all the trainings but it was essentially a two-day heavy course of a SAFe consultant telling us how to run dailies, groomings, plannings, PI plannings, retros, demos etc. etc. ALL of these were mandatory and our team was assigned a Scrum master to make sure we were actually doing them (granted, he took responsibility of organizing also the retros, which was previously a full workday for me every two months.)
I even remember reading from the SAFe book that teams are only afforded a limited autonomy of deciding on the implementation technologies of the features that are assigned. No word of having any autonomy over the process, since I understod the uniform process being a requirement for the inter-team coordination to work.
I guess you just weren't Agileing and Scruming hard enough!
I would argue that most companies cannot afford to give that kind of "empowerment" to most developers, especially if these companies rely heavily on masses of junior/inexperienced developers. So they figure a strong management layer is necessary to properly direct the project's goals.
Now I'm not saying that's how it should be, but that's the reality of the software talent market today.
The problem is that this means you need leaders—managers or not—who are comfortable without an illusion of control or visibility and who understand how to lead and communicate effectively. And you really need this all the way up the chain. If you manage this, though, you'll be amazed at how productive even heavily junior teams can be.
Development isn’t an assembly line process—and cannot possibly be. It’s about theory building and mental models. It requires experience.
It’s fine to have juniors, but they need to lean heavily on experienced colleagues. No amount of management and no management process can change that. A team where the juniors outnumber the seniors 3-to-1 is going to cost more money in the long run.
What you’re describing is exactly what I’m talking about when I say companies are unable to achieve this. Hire 3 senior people instead of 12 junior. You’ll get more done. Reduce your collaboration costs. But, as a manager, you get paid more if you manage more people, or if the people below you manage more people, so there’s a perverse incentive to build as much bureaucracy as possible and staff the lowest layers with the cheapest possible hires.
Personally I'd almost always rather hire a single senior engineer and pay them what two juniors make. I suspect I won't get double the JIRA throughput, but will get more than double the actual effect on the product.
Anyone who says the Agile Manifesto and Scrum are not directly at odds is trying to sell you something.
If you never seen this, you should read this ASAP: https://agilemanifesto.org/
Because that's all there is to know about Agile. Obviously it takes a bit more time to really grasp how can you translate that to lines of code or building a deployment pipeline or shipping features, but if you understand these couple of lines, you already know enough about agile development.
“Kids today don’t know” what it feels like, explaining lawyers how you didn’t feel the wind turning after spending 9 months delivering layer 1 and 2 and crossing your fingers that layer 3 will be a wrap-up. Once you have seen that, the “less paperwork, more interactions”, the “add value not layers” become a relief ;)
But more seriously, "agile", what does it even mean? I almost posted this on another comment.
There is no, singular, agile beyond the manifesto. Everything else is a variation either attempting to push the goals and ideas of the manifesto or attempting to capitalize on fads.
Scrum is borderline fad (I'm ok on the concept, but I think employees should be paid not to go to most Scrum classes; most implementations are incredibly badly done like they deliberately misread the guide). SAFe is bullshit (the gov't bought into it though, how's that F-35 coming along again?).
XP had (has?) some seriously dogmatic advocates, but most people have learned it's a toolkit and not a thing to do without consideration.
Lean has always been presented as a philosophy and toolkit, at least as far as everything I've ever been able to find on it. I think there are some moronic certifications out there, skip them.
DevOps is Theory of Constraints for IT. Which is not a set of ceremonies to perform, but a way of viewing and trying to improve the system. Though, like with Lean, many people are apparently illiterate and fuck it up.
So the question becomes: what version of "agile" were you using? And did you do one of the most important thing that, as I noted in another comment, seems to be the most crucial common element of most of these (except SAFe, fuck SAFe): Did you actively set about to improve the way you worked as you worked? Did you frequently ask questions like: Is this working for us? Is this working for our customers? Is this the right process? Are these the right tools? Are we holding it right or should we try something different?
If introspection and reflection and periodic adjustments to not just the product but also the team (structure and dynamics) and processes aren't in play, then it's probably a ritualized version of agile which is only barely better than Waterfall.
Continue this thread — 1 reply
Very high quality engineering work has been getting done ages before "agile" status-reporting was invented and it was often not waterfall (I've been around the industry since the 80s and have never done "waterfall" - the false dichotomy of agile vs. waterfall is a myth).
Much like TDD, which works great when it’s dev driven, agile works great when it’s driven by dev team.
The problem happens when the PMs get involved and they have to schedule meetings to get basic status updates and have to implement their voodoo rituals to make it look like PMs are adding to project velocity. Planning Poker, lol.
It gets much worse on larger scope projects and many devs and PMs are inexperienced.
SAFe has a great, telling name though - it's designed to be safe for corporate control freaks. They might not know waterfall, they just live it in their guts.
Easy to identify, they believe in being a "visionary leader" and "inspiring the lower rank".
If you have an inexperienced team, any process you adopt is going to suck.
Talking with a customer was great when we could, usually it's been when I worked in a small team (1-3 developers), speaking with either internal or external customers. We talk through what is needed then the BA/PM documents it in the updated job brief, rather than the other way around which leads to so much back and forth. It gets to the root of any uncertainty about what they want much quicker.
This is not any official brand of Agile. It's just our natural inclination when left alone. Talk, iterate, deliver.
I'd rather have multiple Sr. Devs be half time management, and half time dev. Or increase Sr. Dev pay by 20-30% and have them pick up management on top of their duties.
Sprints conceptually make sense. We have 3 features we want to develop. Lets aim to complete them in the next 2-3 weeks. I like them so long as the goals are extremly well defined and managed. Too many teams though forget the agile aspect of agile development. If there's a change to the priorities, its often poorly communicated or just added to the sprint without removing anything.
Daily Standups, as practiced by most teams, are a waste of time. They become status updates for the Project Manager or Team Leader.
What would be better is for engineers to use the time to review ideas, issues that have cropped up and ask questions about the codebase or specific issues. This is probably what a standup is supposed to be but when its mixed in with the context of status updates, it always takes a back seat.
Pointing is a complete waste of time. I have no idea how long a ticket is going to take until I start working on it. Estimations are usually wrong anyway. If anything, tickets should be pointed once the work is complete to track a teams acutal performance and velocity (output).
Having the team review tickets for the next sprint (sprint planning) is useful for inital discovery (so long as it doesn't involve pointing). One person on your team might know how to solve a bug ticket or know if a feature ticket is deceptively difficult. That discovery process can be extremely valuable.
Overall agile ideas I think do help more than they hurt but not always and not by much.
If the feature or task takes longer than the allotted time, you get to be agile and reevaluate if you should continue on the feature (does it need just a bit more work) or if its something to come back to in the next cycle.
Just like you say. If something takes longer than expected in the sprint, the retro is the time to call it out, review what happened that made the ticket take longer than expected and share your learnings with the team so everyone is aware of that particular aspect and knows to look out for it next time (maybe it was waiting on another team that blocked you, an unseen complexity, a changing requirement etc).
Continue this thread — 3 more replies
Something I consider maintenance work is refactoring of systems as new projects are planned/implemented. Everyone knows it’s a bad idea to just bolt on more and more “feature” work without thinking systemically, then we all point at “systemic” issues in retrospective meetings.
Again though, I’m not losing any sleep over this it’s just an observation from 9 years of experience as a web developer working for mostly SV tech companies large and small. It won’t be everyone’s experience, and in general the best advice I can give is try to come up with solutions using your own experience and opinions over those people implicitly/explicitly tell you to follow because they are “good”.
Continue this thread — 3 replies