what are the pros and cons of sprints and daily standups in your experience

Coming from old school 'non-agile' financial world focused on bottom line I was in a bit of a shock learning about this daily standup ritual.
Besides being a dream for micromanagers, it seems to be more about signalling progress vs. actually making progress.
Do these extra bureaucracy layers, meetings, checkmarks and vague "man-points" estimates actually bring any value.

Comments (695) 225 threads

Earlier comments
meheleventyone1 reply#
Agile the stuff in the manifesto is pretty much spot on.

Agile the stuff people make you do in work is often pretty anti-thetical.
Scrum as a process is basically poison.

jamesrr391 reply#
Upvoted (although I'm not sure I agree with the last point, but the top 2 are definitely spot-on)

The agile manifesto is tiny and a scrum guide like this one: https://scrumguides.org/scrum-guide.html is readable in a couple of hours. But the version of "scrum" forced on many people is a far cry from that.

meheleventyone1 reply#
For the last one, basically if a process is essentially never implemented in a way that respects the principles it’s designed around something is very wrong.
jamesrr396 replies#
Yes, I agree. But I'm not sure what you do about that though. Stronger "dictacts" from an international "scrum committee" putting out material telling you what is "correct" scrum and what is not?

Continue this thread — 6 replies

ChrisMarshallNY1 reply#
I have not had good luck with organized agile. I like the manifesto, and the pedigree of its authors. I just have been unable to be satisfied with its actual implementation. Probably my fault (or my company’s).

Nowadays, because folks don’t like to work with older devs, I’m forced to work alone. Although this limits the scope of what I can do, it has allowed me free rein to formalize a manner of programming that has very good results.
I call it “Evolutionary Development”[0]-[2]. It requires a great deal of experience (not intelligence or education). Thankfully, that’s a resource I have in abundance.
[0] https://littlegreenviper.com/miscellany/evolutionary-design-...
[1] https://littlegreenviper.com/miscellany/forensic-design-docu...
[2] https://littlegreenviper.com/various/concrete-galoshes/

madeofpalk1 reply#
> I just have been unable to be satisfied with its actual implementation

You have not been satisfied with implementations you've experienced.

ChrisMarshallNY1 reply#
Exactly. That’s why I phrased it that way. But the way I do things now, would give a lot of agile folks fits.

If I’m skating on thin ice; I might as well dance.
EDIT: It looks like you got dinged for that comment. I'm sorry. It was a bit challenging, but completely fair, done in a respectful manner, and I respect it. I expect and support that kind of challenge on HN.

madeofpalk#
The true agile practitioners would be happy you've found a process that works :)
unethical_ban1 reply#
I like the idea of Kanban and 3x weekly standups/status.

VS
Sprints and daily standups.
---
Daily standups are too often, not enough updates, and it feels more like pressure than utility for the engineers.
Sprints, while helping keep multiple teams working on a single "epic" or "feature" in sync, also feel like an arbitrary slice of time vs. letting people work on things at the pace they are comfortable at. Finish early? Careful taking new work in, it will look bad to bring new things into the sprint and not finish.
Take an extra day on a story due to some complications? That's fine if it's middle of sprint. But rollover into new sprint? Oh gosh, what will that do to our sprint report?
Time estimations, maintaining backlogs of work and prioritizing, and documenting work done are all great. But some of it has too much ritual to it.

natoliniak#
> Careful taking new work in, it will look bad to bring new things into the sprint and not finish

yep. Furthermore, there are many other perverse incentives that I noticed, but one stands out: the incentive not to take on risky or difficult stories out of fear that if it is not finished by the "committed" date (end of sprint), you will be tarred and shamed during the sprint review.

Osiris2 replies#
I've used both Scrum and Kanban. Kanban, for me, is by far the superior method. There are no artificial sprint deadlines, no ticket sizing, far fewer ceremonies, gives a lot of flexibility, but still provides enough structure to place emphasis on tracking and completing work.

If you've never worked in a Kanban environment, I highly suggest you research it and encourage your employer to experiment with it.

perlgeek1 reply#
Note that Kanban requires a certain maturity and self-discipline from the development team and the stakeholders. If that's a given, Kanban can work very well.

Scrum was really invented for situations where management is constantly asking "when do we get X?" and the development always says "we aren't done yet".
In this scenario, the sprint is meant to reassure management that they'll get at least *something (even if not a full X) in a predictable time, and forces the development team to put something out in a given time frame even if not yet perfect / finished / whatever.
If that's not a problem, Kanban can be indeed be a much better fit, and come with far less overhead.

pracer#
> the sprint is meant to reassure management that they'll get at least *something (even if not a full X) in a predictable time

I would rephrase it as "sprint is meant to make management to believe that they'll get at least something in a predictable time".
I also notice that lots of comments seem to be coming from front-end or customer-based companies. For backend and b2b, 2 weeks sprint for some new functionality is funny.

tarcon1 reply#
A team commitment based on the learning from the last sprints to scope the next one, so that you can predict the delivery scope, is an artificial deadline?
Too#
Yes. Either "commitments" are ignored and tickets casually spill over into next sprint, or they are enforced leading to inflated estimates by the team so you dont have to work overtime the next sprints. See also the commitments-vs-forecast discussion further above.

Kanban still has estimates and you can still do bi-weekly demos of whatever has been done since last demo. Management can still get a sense of when they will get stories by judging how far down the backlog they are. Team is still protected from interruptions by their WIP-limit but PO can still swap out highest prio item not currently in progress, win-win.