I work at a startup with ~50 employees (and have always worked at startups). Love the work and the people. Recently we were acquired by $LARGE_CORPORATION and the experience has been a living hell for all of us. Things that should take a few days take a few weeks. Things that should take a few weeks take a few quarters. It's slowly driving me insane.

The experience is best shared as a story.
I'm working on migrating our apps to the parent company's VM launching and deploy platform. Should be fairly straightforward, I think. Unfortunately, the deploy tooling isn't entirely compatible with our app so I ask the team if they can implement $X feature to support our app.
The first engineer I talk to doesn't even attempt to answer my question but redirects me to their manager. Ok, that's odd, I think, but whatever.
Manager says sure, just fill out this feature request doc. It's a Google Docs template with 4 (!) pages of required documentation to just explain why I want this feature implemented. It asks for my team name, the motivation, why I can't solve the problem some other way, yada yada...ok, I guess it's good to document your work, so sure. I fill it out and submit it.
No response after two days. Then I get an automated email that their skip level manager has approved the work. Huh? This is followed by an email that the team's eng manager approved the work. Why do two layers of management need to approve work on something they have no knowledge about?
Finally, after many rounds of arguing about why this needs to be done in the first place (ahem: you told us to migrate to your platform, and it literally does not work for our app), they quote us a delivery timeline of end of Q1 in 2022.
At this point I am in absolute shock. This should take no more than a few days to implement.
So I reach out to the manager and ask what is going on. This is a simple task, I said. Why does it take an entire quarter for your team to deliver? He doesn't have an answer.
I tell him I'm happy to fix the issue myself, if they link me to the relevant codebase. "It shouldn't be too hard to dig in and submit a patch," I think to myself. He says he cannot give me access to the codebase for compliance reasons, and that only members of his team have R/W on that repo. What???
This is insane. And this entire time I was only alllowed to interact with managers and have not spoken to a single engineer about the actual technical details. It is impossible to get anything done here now.
Is this how it's like at all large companies? What should I do?

Comments (444) 193 threads

Earlier comments
Johnny555#
End of Q1 2022 for a significant feature sounds reasonable for a large company (a few days to implement means a few weeks once you include design, documentation, review, implement, test, deploy).

It's annoying, but everything takes longer in a big company because every change you make can affect many teams/customers, and it's very hard to get unscheduled project work done quickly unless it's a real emergency.
Your best response is to make porting your apps to their platform dependent on that change, so you can't do it before end of 2022Q1, escalate the dependency to your manager so he/she can either elevate the priority of the feature you need, or just live with the timeline.
It's annoying for sure, I work at a growing company that used to be a small startup and am often dismayed at how long it takes to do even trivial changes, but am also reminded of the time that we accidentally caused a full outage for all of our customers with a config change that was deployed everywhere before we discovered a problem. We didn't bake it fully in the QA system (where we would have discovered the problem) because everyone "knew" it was a harmless change similar to others that we make all the time. We esentially applied it to QA to verify the syntax, then rolled it out globally, where it ran fine for a few days before filling up some temp space. So now it takes at least 2 weeks to roll out those "simple" changes due to mandatory documentation and testing.

BurningFrog#
You're clearly a startup person, and won't be happy at $LARGE_CORPORATION.

You should probably accept this as a fact, and figure out what your next startup will be. Join an existing one, start something with some equally frustrated coworkers?
You have some time to figure it out. Just like it takes them 6 months to do your simple code change, it'll take them as long to fire you if you stop working.

talolard#
I worked at Citi for a while and this pain sounds familiar. It once took me 6 months of hounding an MD to get approval for my app to connect to a particular database.

It sounds like you're very motivated and presumably talented, but the organizational friction doesn't really allow for your blessings to shine.
On the other hand, this is the reality for many many people and many many dollars. It's a great opportunity to both develop empathy for a kind of user you never imagined (all those people trapped in these processes for life) and to learn new ways to excel, within the context you're currently in.
When I was at Citi I learned a lot about communicating with stakeholders and fostering internal relationships which has been very useful in my career. Maybe you can find the same there ?

Merad#
> So I reach out to the manager and ask what is going on. This is a simple task, I said. Why does it take an entire quarter for your team to deliver? He doesn't have an answer.

Have you never worked on a team that had work planned out months in advance? Usually IME the team will only plan out the next quarter in any detail since things always change. But the product team and managers often have a roadmap (high level plan) extending out a year or more.
Most likely this team has already planned their Q1 and has given commitments to stakeholders, etc. For your work to jump to the head of the queue it would need to be more important than what they've already planned. Yes, maybe your request only takes a few days, but odds are that the team has dozens of requests on their backlog that are just a few days worth of work. If you want to try to get them to prioritize this work then someone from your team (typically PO, PM, or manager) needs to reach out to the other team and communicate what the impact to the company will be if your team is blocked for the entire quarter.
P.S. - Sort of a tangent, but this scenario is one where a good scrum master is worth their weight in gold. Once you communicate to the team that your work is blocked the SM can take on figuring out who needs to talk to who to try to prioritize the work, and will stay on those people to follow through so that you know when you'll be unblocked and the team can adjust plans accordingly. It may sound like a small thing, but it's wonderful not having to deal with it yourself as an engineer.