Ask HN: Inherited the worst code and tech team I have ever seen. How to fix it?
557 points- this code generates more than 20 million dollars a year of revenue
- it runs on PHP
- it has been developed for 12 years directly on production with no source control ( hello index-new_2021-test-john_v2.php )
- it doesn't use composer or any dependency management. It's all require_once.
- it doesn't use any framework
- the routing is managed exclusively as rewrites in NGInX ( the NGInX config is around 10,000 lines )
- no code has ever been deleted. Things are just added . I gather the reason for that is because it was developed on production directly and deleting things is too risky.
- the database structure is the same mess, no migrations, etc... When adding a column, because of the volume of data, they add a new table with a join.
- JS and CSS is the same. Multiple versions of jQuery fighting each other depending on which page you are or even on the same page.
- no MVC pattern of course, or whatever pattern. No templating library. It's PHP 2003 style.
- In many places I see controllers like files making curl requests to its own rest API (via domain name, not localhost) doing oauth authorizations, etc... Just to get the menu items or list of products...
- no caching ( but there is memcached but only used for sessions ...)
- team is 3 people, quite junior. One backend, one front, one iOS/android. Resistance to change is huge.
- productivity is abysmal which is understandable. The mess is just too huge to be able to build anything.
This business unit has a pretty aggressive roadmap as management and HQ has no real understanding of these blockers. And post COVID, budget is really tight.
I know a full rewrite is necessary, but how to balance it?
Comments (676) 322 threads
Earlier commentsFrom the HQ perspective they make a lot of money with very few developers and all seems to be going well, with no problems at all. Judging by the spreadsheets this looks great!
Your task is now to explain to them the risks involved with proceeding forward. You can also present them a plan to mitigate that risk without interrupting ongoing operations too much and slap some money figure on it — ideally you present them three options where one of those is doing nothing. Be aware that the decision on this is not yours, it is theirs. Your task is to tell them everything relevant for that decision. You can also tell them, that your professional opinion is that this is something that ahould have been done years ago and the fact that this didn't explode in their faces yet was pure luck. But again it is their decision.
How you lay it out depends on you, but there have been many tips already. Version control might be the first thing. Maybe you can present it as: one day a week goes towards maintenance or something.
As an aside this helps to cover your own behind if nothing is done and everything goes south in a year. Then you can point to that extensive risk analysis you presented them with and tell them you told them so.
I'll share some less technical thoughts that I think hold true regardless of the approach taken (rewrite or not).
My experience with changes like this is that you need to be as transparent as possible to both parties (the devs, and your execs). This means consistent comms around goals, achievements, and crucially the challenges preventing the first two.
With any team, you are not going to win much by implying that their work sucks or the thing they have built is broken. While they might know it, a third party is just not going to get a good reception with that mentality. It will be important for the devs to understand why the change is needed from a business perspective (e.g. time to market is too slow to remain competitive, changing regs, etc.). The intent here is to focus the devs on what the hope is for the future as opposed to shitting over the thing they have poured their blood, sweat, and tears into.
With the execs, they need to understand just how bad of a shape things are in so they give you and the team the space they need to make a significant enough change that isn't just going to revert to the same mess as before. If you're dealing with tech background execs it might be a bit of a simpler set of convos. But if not, then you are going to have to illustrate for them how bad things are. One way I've done this is to first get an idea of what the execs want as the final state of the team / codebase / product (e.g. time to market is < 4 wks) and then draw them a picture/flowchart of what it takes to get that thing done in the current state. Could use some form of value stream map to do this as it combines players, states, activities, and also timelines.
I suggested full rewrite and got fired in 3 weeks (actually it was a subcontractor role). I have been considering myself as be really good at presentations and persuading executive people to understand what I am doing and what I will be doing, but the situation was too much for me to take on. They didn't like this unrealistic 3-months roadmap to rewrite the whole thing, which does nothing on their point of view but still needs paying the whole team (even though I was the only one). So I told them we are gradually improving it, and did this full-rewrite underground on my own. It consumed me ~13 hours every day, but I was happy myself and was enjoying the birth of the product. Finally after 10 weeks, I gave up to myself and their frustration.
Regarding your problem, I totally suggest dumping your codebase into a git repo first of all, add some cypress/playwright testing to carefully probe the major functionalities, build ci for these, and start gradually removing old version files. After then, just forget how messy it was, what you thought in the first place, consider this beast as a perfect engineering gift (like linux kernel), then start making small changes then adapt yourself into it. Guide the team to follow your methodologies to treat the code, and tell the executive team that the legacy codebase looks great but complex enough to move quickly as it was a brand new startup project.