Console is flickering between "website is unavailable" and being up for my team. This is happening very frequently just now, reliability seems to have taken a hit.

Comments (614) 80 threads

aledalgrande7 replies#
If you haven't seen yet, news is it was a power loss:

> 5:01 AM PST We can confirm a loss of power within a single data center within a single Availability Zone (USE1-AZ4) in the US-EAST-1 Region. This is affecting availability and connectivity to EC2 instances that are part of the affected data center within the affected Availability Zone. We are also experiencing elevated RunInstance API error rates for launches within the affected Availability Zone. Connectivity and power to other data centers within the affected Availability Zone, or other Availability Zones within the US-EAST-1 Region are not affected by this issue, but we would recommend failing away from the affected Availability Zone (USE1-AZ4) if you are able to do so. We continue to work to address the issue and restore power within the affected data center.

codeduck1 reply#
another example of a single dc in a single AZ rendering an entire region almost unusable. This has shades of eu-central-1 all over again.
nightpool4 replies#
Amazon is claiming the failure is limited to a single AZ. Are you seeing failures for instances outside of that AZ? If not, how has this rendered "the entire region almost unusable"?
londons_explore3 replies#
A lot of people will automatically fail over jobs to other AZ's. That often involves spinning up lots more EC2 instances and moving PB's of data. The end result is all capacity on other AZ's gets used up, and networks get full to capacity, and even if those other zones are technically working, practically they aren't really usable.

Continue this thread — 3 replies

tyingq#
Perspective, I would guess. Unless you spend a lot of time on retry/timeout/fail logic around AWS apis, your app could be stuck/blocked in the RunInstances() api, for example.
matharmin2 replies#
Yes, I've seen issues that affected the entire region. In my specific case, I happened to have an ElastiCache cluster in the affected AZ that became unreachable (my fault for single AZ). But even now, I'm unable to create any new ElastiCache clusters in different AZs (which I wanted to use for manual failover). And there were a lot of errors on the AWS console during the outage.

"almost unusable" is maybe exaggerating, but there were definitely issues affecting more than just the single AZ.

Continue this thread — 2 replies

codeduck4 replies#
We've had alerts for packet loss and had issues in recovering region-spanning services (both AWS and 3rd party).

Yes, some of these we should be better at handling ourselves, but... it's all very well to say "expect to lose an AZ" but during this outage it's not been physically possible to remove the broken AZ instances from multi-AZ services because we cannot physically get them to respond to or acknowledge commands.
edit: just to short circuit any "well, why aren't you running redundant regions" - we run redundant regions at all times. But for reasons of latency, many customers will bind to their closest region, and the nature of our technology is highly location-bound It is not possible for us to move active sessions to an alternate region. So something like this is... unpleasant.

Continue this thread — 4 replies

GrumpyNl8 replies#
How come they dont have power backups?
trelane1 reply#
Anything can fail, even your backup, and especially if it's mechanical.
rdines#
The battery backups (called uninterruptible power supplies) are only meant to bridge the gap between the power going out and the generator turning on, which is a few minutes. Did they say power was the issue this time? I suspect it’s actually something else (ahem network)
2-718-281-82814 replies#
is that just playing with words?

Continue this thread — 14 replies

thetinguy1 reply#
They do. I remember watching one of their sessions where they showed every rack having its own battery backup.
tyingq#
An article on that: https://datacenterfrontier.com/aws-designs-in-rack-micro-ups...

Interesting quote:
“This is exactly the sort of design that lets me sleep like a baby,” said DeSantis. “And indeed, this new design is getting even better availability” – better than “seven nines” or 99.99999 percent uptime, DeSantis said.

taf21 reply#
it was not a total power loss. out of 40 instances we had running at the time of the incident only 5 of our instances appeared to be lost to the power outage. the bigger issue for us was ec2 api to stop/start these instances appeared to be unavailable (but probably due to the rack these instances were in having no power). The other issue that was impactful to us was that many of the remaining running instances in the zone had intermittent connectivity out to the internet. Additionally, the incident was made worse by many of our supporting vendors being impacted as well...

IMO it was handled rather well and fast by AWS... not saying we shouldn't beat them up (for a discount) but being honest this wasn't that bad.

res0nat0r#
If the rack your instances are running in are totally offline then the ec2 api unfortunately can't talk to the dom0 and tell the instances to stop/start, so you get annoying "stuck instances", and really can't do anything until the rack is back online and able to respond to API calls unfortunately.
TrueDuality#
According to the SOC certifications they give their customers they do.
redm#
Some datacenter failures aren't related to redundancy. Some examples: 1) transfer switch failure where you can't switch over to backup generators and the UPS runs out, 2) someone accidentally hits the EOD, 3) maintenance work makes a mistake such as turning off the wrong circuits, 4) cooling doesn't switch over fully to backups and while your systems have power, its too hot to run. The list can go on and on.

I'm not sure why this is a big deal though, this is why Amazon has multiple AZ's. If your in one AZ, you take your chances.

Spooky23#
Their datacenter(s) aren’t magic because they are AWS. That facility is probably a decade old and like anything else as it ages the technical and maintenance debt makes management more challenging.
chousuke1 reply#
Sometimes, you have a component which fails in such a way that your redundancies can't really help.

I once had to prepare for a total blackout scenario in a datacenter because there was a fault in the power supply system that required bypassing major systems to fix. Had some mistake or fault happened during those critical moments, all power would've been lost.
Well-designed redundancy makes high-impact incidents less likely, but you're not immune to Murphy's law.

macintux1 reply#
To my mind, among the more frustrating aspects to implementing protection against failure is that the mechanisms to be added can themselves cause failure.

It's turtles all the way down.

Continue this thread — 1 reply

vinay_ys2 replies#
This is quite interesting as they claim their datacenter design does better than Uptime's Tier3+ design requirements which require redundant power supply paths. [https://aws.amazon.com/compliance/uptimeinstitute/]. I really hope they publish a thorough RCA for this incident.
tyingq4 replies#
"Electrical power systems are designed to be fully redundant so that in the event of a disruption, uninterruptible power supply units can be engaged for certain functions, while generators can provide backup power for the entire facility." https://aws.amazon.com/compliance/data-center/infrastructure...

So they have 2 different sources of power coming in. And generators. They do mention the UPS is only for "certain functions", so I guess it's not enough to handle full load while generators spin up if the 2 primaries go out. Or perhaps some failure in the source switching equipment (typically called a "static transfer switch").
Some detail on different approaches: https://www.donwil.com/wp-content/uploads/white-papers/Using...

vinay_ys1 reply#
Usually when someone claims T3+ they mean they have UPS clusters in 3+1 (or such) configuration and two different such UPS clusters power two power-strips in a rack. Then, would also have incoming grid power supply from two different HV sub-stations with non-intersecting cable paths. They would also have diesel power generators in 3+1 or 5+2 configurations with automatic startup time in seconds. The UPS's power storage (chemical or potential energy based devices) can hold enough energy to handle full load for several minutes. If these are design and maintained correctly, even while concurrent scheduled maintenance is ongoing, an unexpected component failure should not cause catastrophic outage. At each layer (grid incomers, generator incomers, UPS power incomers) there are switches to switch over whenever there's a need (maintenance or failure).

If they claim tier4, then they basically have everything in n+n configuration.

Continue this thread — 1 reply

dylan60411 replies#
The generators should be powering up as soon as one of the 2 different sources goes down. It takes generators a few minutes to power up and get "warmed up". If they don't start this process until both mains sources are down, then oops, there's power outage.

I used to work next door to a "major" cable TV station's broadcast location. They had multiple generators on-site, and one of them was running 24/7 (they rotated which one was hot). A major power outage hit, and there was a thunderous roar as all of the generators fired up. The channel never went off the air.

Continue this thread — 11 replies

Continue this thread — 2 more replies

Continue this thread — 1 more reply

Continue this thread — 4 more replies

ItsBob6 replies#
I've built out many 42U racks in DC's in my time and there were a couple of rules that we never skipped:

1. Dual power in each server/device - One PSU was powered by one outlet, the other PSU by a different one with a different source meaning that we can lose a single power supply/circuit and nothing happens 2. Dual network (at minimum) - For the same reasons as above since the switches didn't always have dual power in them.
I've only had a DC fail once when the engineer was performing work on the power circuitry for the DC and thought he was taking down one, but was in fact the wrong one and took both power circuits down at the same time.
However, a power cut (in the traditional sense where the supplier has a failure so nothing comes in over the wire) should have literally zero effect!
What am I missing?
I've never worked anywhere with Amazon's budget so why are they not handling this? Is it more than just the imcoming supply being down?

uluyol1 reply#
Why spend the cost on dual X and Y when you can failover to another cluster?

For big DC workloads, it is usually, though not always, better to take the higher failure rate than add redundancy.

ItsBob1 reply#
Really? You'd think at Amazon's scale an additional PSU in a 1U custom-built server (I assume they're custom) would be a few tens of $ at most.

Actually, now that I type that it makes sense. Scaling a few tens of dollars to a bajillion servers on the off-chance that you get an inbound power failure (quite rare I'd reckon) might cost more than what they'd lose if it does actually fail.
So yeah, they're potentially just balancing the risk here and minimising cost on the hardware.
Edit: changed grammar a bit.

vel0city1 reply#
At big cloud provider scale like Amazon, Azure, and Google they probably aren't even running PSUs at each server, they're probably doing DC at the rack these days. No point in having a million little transformers everywhere, far easier maintenance centralizing those and have multiple feeding the bus bars going to each rack.

Continue this thread — 1 reply

Bluecobra1 reply#
> What am I missing?

My guess is that they cheaped out in having redundant PSUs to get you to use multiple availability zones. (More zones = more revenue)
Even a single PSU shouldn’t be an issue if they plugged in an ATS switch though.

Godel_unicode2 replies#
Unless the ATS breaks, which happens.
Bluecobra#
For sure, in my context I meant a ATS in single rack/cabinet. If that went bad the blast radius would be contained to a single cabinet. But yeah, anything can and will happen. At another place I worked at, a site UPS took down an entire server room. It was pretty nice Eaton system but there was some event that fried the whole thing. Eaton had to send an specialist to investigate the matter as those events are pretty rare.
notyourday5 replies#
> I've only had a DC fail once when the engineer was performing work on the power circuitry for the DC and thought he was taking down one, but was in fact the wrong one and took both power circuits down at the same time.

This is all local scale. Your setup would not survive a data center scale power outage. At scale power outages are datacenter scale.
Data centers lose supply lines. They lose transformers. Sometimes they lose primary feed and secondary feed at the same time. Automatic transfer switches cannot be tested periodically i.e. they are typically tested once. Testing them is not "fire up a generator and see if we can draw from it"
It is cheaper to design a system that must be up which accounts for a data center being totally down and a portion of the system being totally unavailable than to add more datacenter mitigations.

ItsBob2 replies#
Yes but if you have reliable power from two different sources then the biggest risk (I'd imagine) is the failover circuitry! Something that should be tested tbh.

Also, there are banks of batteries and generators in between the power company cables and the kit: did they not kick-in?
Again, this is all pure speculation: I have absolutely no idea of the exact failure, nor how their infrastructure is held together - this is all just speculation for the hell of it :)

merlyn#
Frying hardware can affect much wider scope.

I've had bad power supplies fry out taking the whole power circuit with it, and thus half (or whatever fraction) of the rack's power. I've also had bad power supplies bring down the whole machine as they shunted everything internal too.
When things go bad, anything can happen. You can provide the best effort, and it'll usually work as expected, but there will always be something that can overcome your best efforts.

notyourday2 replies#
> Yes but if you have reliable power from two different sources then the biggest risk (I'd imagine) is the failover circuitry! Something that should be tested tbh.

That's ATS. It is not really advisable to test their under load performance because the failure of an ATS would be catastrophic. ATS typically would be tested at the installation and after that their parameters would be monitored.
Replacing a functional in line ATS would be a 9-12 months long project.
> Also, there are banks of batteries and generators in between the power company cables and the kit: did they not kick-in?
At high energy you are pretty much always going to use an ATS.

Continue this thread — 2 replies

bombcar1 reply#
The datacenter we were in had dual-sourced grid power (two separate grid connections on opposite sides of the block, coming from different substations) along with a room of batteries (good for iirc 1hr total runtime for the whole datacenter, setup in quad banks, two on each "rail"), _and_ multiple independent massive diesel generators, which they ran and switched power to every month for at least an hour.

And to top it off each rack had its own smaller UPS at the bottom and top, fed off both rails, and each server was fed from both.
We never had a power issue there; in fact SDGE would ask them to throw to the generators during potential brown-out conditions.
Of course this was a datacenter that was a former General Atomics setup iirc ...

Continue this thread — 1 reply

Continue this thread — 3 more replies

Continue this thread — 3 more replies

Hippocrates20 replies#
Every time a major cloud provider has an outage, Infra people and execs cry foul and say we need to move to . But does anyone really have an objective measure of how clouds stack up reliability-wise? I doubt it, since outages and their effects are nuanced. The other move is that they want to go multi-cloud... But I’ve been involved in enough multi-cloud initiatives to know how much time and effort those soak up, not to mention the overhead costs of maintaining two sets of infra sub-optimally. I would say that for most businesses, these costs far exceed that occasional six-hour-long outage.

Continue this thread — 20 replies

hnarn9 replies#
Is there a history of AWS downtimes available somewhere? This makes what, three times in as many months?

edit: The question isn't necessarily AWS specific, just any data on amount of downtime per cloud provider on a timeline would be nice.

Continue this thread — 9 replies