Ask HN: Azure has run out of compute – anyone else affected?
651 pointsLast week we at n8n ran into problems getting a new database from Azure. After contacting support, it turns out that we can’t add instances to our k8s cluster either. Azure has told they'll have more capacity in April 2023(!) — but we’ll have to stop accepting new users in ~35 days if we don't get any more. These problems seem only in the German region, but setting up in a new region would be complicated for us.
We never thought our startup would be threatened by the unreliability of a company like Microsoft, or that they wouldn’t proactively inform us about this.
Is anyone else experiencing these problems?
Comments (341) 92 threads
Show all comments
Showing thread 29 of 92
Something to try in scenarios like this is to add the “weird and wonderful” VM SKUs that are less popular and may still have capacity remaining.
For example, the HPC series like HBv2 or HBv3. Also try Lsv3 or Lasv3.
Sure they’re a bit more expensive, but you only have use them until April.